PROJECT | REHABILITATION AND EXTENSION OF THE EL-ABBASSA WATER SUPPLY SYSTEM (EL-SHARKIA GOVERNORATE) |
DESCRIPTION | Raw water pumping station, distribution shaft, underground reservoirs, chemical and chlorination equipment, treated water pumping station, workshops etc…Distribution network of 369 km pipes Ø 300-1200 mm. The works include the rehabilitation of 6 boosting stations, new elevated reservoirs, 1000-4000 m3, and ground reservoirs with capacities 4000-20000 m3. |
CLIENT | National Organization for Potable Water and Sanitary Drainage (NOPWASD) |
LOCATION | EGYPT |
SCOPE OF SERVICES | Data collection, Surveying, Engineering design including hydraulic, mechanical electrical and civil. Preparation of technical specification and tender documents for both mechanical and electrical equipment and civil work. |
COMMENCING DATE | |
COMPLETION DATE |